Area residents, Public Safety team members, and the HW School District are notified of any updates to the construction schedule. A representative from JJ Phelan will always been on site to work with residents and any public safety team members in the event that emergency access is needed during construction.
Please contact Jackie Bresnahan at jbresnahan@wenhamma.gov or call 978-468-5520 x.6 for more information.
Construction Schedule for Longfellow Road
Week of 10/26/20
Erosion Control Installation
Tree Removal
Week of 11/2/20
Clear and Grub Site
Construct Keyway at bottom of slope
Week of 11/9/20
Construct Slope Sub-grade and Install RIP RAP
Week of 11/16/20
Continue Slope Sub-grade construction and RIP RAP installation
Week of 11/23/20
Continue Slope RIP RAP installation
Retaining Wall Construction
Week of 11/30/20
Finish Retaining Wall construction
Full Depth Pavement Reconstruction
Week of 12/7/20
Continue Full Depth Pavement Reconstruction
Install Guardrail and Fence
Install signage
WEATHER PENDING: Pave roadway
Week of 12/14/20
Project close out